The Armenian Heritage Walk will be divided into two phases, each with its own scope and timeline.

PHASE ONE
The Walk and Statue Revival

PHASE TWO
and Beyond

Scope includes all the landscaping, hardscaping, irrigation, and lighting for the new Armenian Heritage Walk. This includes the trees, pavers, curbing, boulders, and flowers in the image above.
 
The complete revival of the "Young Meher" statue:

  • Full restoration of the statue and four relief panels

  • Existing statue base replaced with two solid granite blocks

  • Repositioning the statue ~25 feet east to its final position

  • Rotating the statue 90° to face east toward Armenia

Scope includes the design, creation, and installation of new artwork within each station of the Walk.

​

The themes, style, geometry, material, and meaning behind each new piece of artwork is under development.

May 2024

Final Engineering Plans

July 2024

Building Permits

Final Statue Revival Plan

August 2024 

Material Procurement Begins

April 2025

Phase 1 Groundbreaking

Construction Begins

April 2026

Phase 1 Unveiling 